Projects 2024 MBR-2024-04

Master Bath Renovation

In progress · Webb Construction LLC · License #CA-48821
Day
Contract
$47,500
fixed price
Invoiced
$28,500
60% drawn
Est. Complete
Apr 19
on schedule
Demolition & prep Mar 25 – Mar 27 Complete
Rough plumbing Mar 28 – Apr 01 Complete
Electrical rough-in Apr 01 – Apr 03 Complete
Tile & waterproofing Apr 03 – Apr 10 In progress
Inspector
City Building Dept.
Inspection date
Apr 07, 2024
Material
Carrara marble 12×24
Grout
Mapei Ultracolor #112
Waterproof membrane — shower floor
Shower wall tile — west & north walls
Floor tile set — in progress
Grouting — pending tile cure

Crane confirmed curing time of 48 hrs before grouting begins. Inspection scheduled for Apr 7 — all membrane work must be complete by Apr 6 EOD.

Fixtures & vanity Apr 10 – Apr 14 Upcoming
Paint & trim Apr 14 – Apr 16 Upcoming
Final inspection & punch list Apr 17 – Apr 19 Upcoming
Today 09:14 Foreman Floor tile layout marked and dry-fit. Starting set this afternoon.
Today 07:52 System Photo documentation uploaded — 14 photos, shower west wall complete.
Apr 02 16:30 Billing Invoice #3 submitted — $9,500. Awaiting owner approval.
Apr 02 11:05 Inspector Electrical rough-in passed inspection. Permit card updated.
Apr 01 14:22 Foreman Change order CO-002 submitted — heated floor element upgrade. $1,200 added.
Mar 28 08:00 System Rough plumbing milestone marked complete. Next: electrical rough-in.