Day
23 / 38
Contract
$47,500
fixed price
Invoiced
$28,500
60% drawn
Est. Complete
Apr 19
on schedule
Milestones
Demolition & prep
Mar 25 – Mar 27
Complete
Rough plumbing
Mar 28 – Apr 01
Complete
Electrical rough-in
Apr 01 – Apr 03
Complete
Tile & waterproofing
Apr 03 – Apr 10
In progress
Inspector
City Building Dept.
Inspection date
Apr 07, 2024
Material
Carrara marble 12×24
Grout
Mapei Ultracolor #112
Waterproof membrane — shower floor
Shower wall tile — west & north walls
Floor tile set — in progress
Grouting — pending tile cure
Crane confirmed curing time of 48 hrs before grouting begins. Inspection scheduled for Apr 7 — all membrane work must be complete by Apr 6 EOD.
Fixtures & vanity
Apr 10 – Apr 14
Upcoming
Paint & trim
Apr 14 – Apr 16
Upcoming
Final inspection & punch list
Apr 17 – Apr 19
Upcoming
Activity
Today 09:14
Foreman
Floor tile layout marked and dry-fit. Starting set this afternoon.
Today 07:52
System
Photo documentation uploaded — 14 photos, shower west wall complete.
Apr 02 16:30
Billing
Invoice #3 submitted — $9,500. Awaiting owner approval.
Apr 02 11:05
Inspector
Electrical rough-in passed inspection. Permit card updated.
Apr 01 14:22
Foreman
Change order CO-002 submitted — heated floor element upgrade. $1,200 added.
Mar 28 08:00
System
Rough plumbing milestone marked complete. Next: electrical rough-in.