Master Bath Renovation
DAY 023 / 038
On track.
Today
Webb Construction is on drywall taping, day 4 of 7. No action needed from you today. The crew is on schedule and tile installation starts March 1 — two days from now. Tile has already been delivered to the site.
After drywall sheets are hung, the seams get sealed with tape and joint compound — applied in 2–3 coats with drying time between each one. It's normal not to see visible progress every day during this phase. Rushing it causes problems later.
Needs your attention
Change order #2 — Heated floor outlet
Webb is requesting an additional electrical outlet for the heated floor you discussed. This adds $800, bringing the total to $51,500.
Review and sign →Budget
6.7% over is within the normal range for a project like this.
Recent activity
- Taping started
- Tile delivered to site
- Electrical inspection passed